Determination Of Contingency Sum For Building Projects In Ghana

Authors

  • J. N.T. Addo Cape Coast Polytechnic

Keywords:

Determination, Contingency Sum, Building, Projects, Ghana

Abstract

The building industry is always surrounded by many risks and uncertainties and their degree in a project results from a combination of factors which differ from one project to another. One of the attempts to handle risks is by allocating project contingency sum. Traditionally, construction professionals determine cost contingency simply by adding; say 10% contingency onto the estimated cost of a project. However, this conventional method is arbitrary arrived at and difficult to justify or defend and coupled with so many associated weaknesses. The aim of the study is to investigate into methods of determining project cost contingency. The specific objectives are :  to identify the existing method(s) of determining project contingency sum in Ghana and to identify the factors influencing the determination of building project contingency sum in Ghana This study has adequately reviewed some methods of determining project contingency sum, factors that influence the determination of project contingency sum in Ghanaian construction industry and elsewhere. A random sampling technique was used to select a sample size of 92 construction professionals practicing. A total of Ninety-Two (92) questionnaires were distributed to the respondents in the building industry out of which 67 representing 72.9% were completed and returned. The collected data on factors were analyzed using the relative important index (5 - most important and 1 - least important rankings). The study identified Deterministic approach (percentage addition) as the most widely known and used method by the construction experts in making provision for contingency. Unexpected ground conditions (substructure works), design consideration, project duration and project specification have also emerged as the most influencing factors.

Author Biography

J. N.T. Addo, Cape Coast Polytechnic

A Lecturer at the Polytechnic

References

Ahmad, I. (1992). Contingency allocation: a computer-aided approach. AACE Transactions, 28, 4-1.

Akinsola, A.O., Potts, K.F., Ndekugri, I., and Harris, F.C. (1997). Identification and evaluation of factors influencing variations on building projects. International Journal of Project Management, 15(4), 263-267.

American Association of Cost Engineers (AACE, 2000). International Risk Management Dictionary Cost Engineering, 42 (4), 28-31.

Baccarini, D. (2004). Accuracy in estimating project cost construction contingency - A Statistical Analysis. In: Robert, E., and Malcolm, B. (eds), Proceedings of the Construction and Building Research Conference of RICS, 7-8 September 2004, Headingly Cricket Club, Leeds. RICS (http://www.rics.org/site/download_feed.aspx?fileID=3460&fileExtension=PDF) (Accessed 2013, October, 19)

Baccarini, D. (2005). Estimating Project Cost Contingency - Beyond the 10% syndrome, Faculty of Built Environment, Art & Design, Curtin University of Technology, Perth, Western Australia. (http://aipm.com.au/resource/Baccarini- AIPMconf05 .pdf)( Accessed 2013, Nov. 9)

Bello, W. A., and Odusami, K. T. (2008). The practice of contingency allocation in construction projects in Nigeria. RICS COBRA. Dublin Institute of Technology, Ireland., RICS, 1-15. (http://www.rics.org/site/download feed.aspx?fileID:=3460&fileExtension=PDF) (Accessed 2013, Oct. 19)

Chen, D., and Hartman, F.T. (2000). A Neural Network Approach to Risk Assessment and Contingency Allocation. AACE International Transactions. Risk.07.01- Risk.07.06.

Clark, F. D., and Lorenzoni, A. B. (1985). Applied Cost Engineering. New York: M. Dekker.

Dey, P., Tabucanon, M. T., and Ogunlana, S. O. (1994). Planning for project control through risk analysis, a petroleum pipelaying project. International Journal of Project Management,12(1), 23-33.

European Commission, DG XVI (1998). Understanding and Monitoring the Cost - Determining Factors of Infrastructure Projects. A User's Guide, Brussels [http://ec.europa.eu/regionaljolicy/source/docgener/evaluation/pdf/5] (Accessed 2013, Dec. 02)

Ford, D.N. (2002). Achieving multiple project objectives through contingency management. Journal of Construction Engineering and Management, 128 (1), 30-37.

Hartman, F.T. (2000). Don't park your brain outside. Project Management Institute. Upper Darby, PA.

Hillson, D. (1999). Developing effective risk responses. PMI Annual Seminar and Symposium,10-16th October, Philadelphia. PMI

Kish, L. (1965). Survey Sampling. New York: John Wiley and Sons Inc..

Kwakye, A. A. (1997). Construction Project Administration in Practice. London: Longman Ltd..

Levine, H. (1995). Risk Management for Dummies: Managing Schedule Cost and Technical Risks and Contingency. PM Network, October, 30-32.

Mak, S., Wong, J., and Picken, D. (1998). The effect on contingency allowance of using risk analysis in capital cost estimating: a Hong Kong case study. Construction management and Economic, 16,615-619.

Mak, S., and Picken, D. (2000). Using risk analysis to determine construction project contingencies. Journal of Construction Engineering and Management, 126(2), 130-136.

Moselhi, O. (1997). Risk Assessment And Contingency Estimating. AACE International Transactions 41, D&RM/A.06.1- D&RM/A.06.6.

Odeyinka, H., Oladapo, A.A., and Akindele, O. (2006). Assessing Risk Impacts on Construction Cost. Proceedings of the annual research conference of the Royal Institution of Chartered Surveyors, Cobra University College, London, 1-13.

Parsons, Jr. E.L. (1999). Waste Management Project Contingency Analysis. Morgantown, West Virginia: Centre for Acquisition and Business Excellence of the United State Department of Energy.

Picken, D.H., and Mak, S. (2001). Risk Analysis in Cost Planning and its Effect on efficiency in capital cost budgeting. Logistic Information Management, 14 (5/6), 318-329.

Project Management Institute, (2000). A Guide to the Project Management Body of Knowledge (PMBOK) PMI (3rd Ed). Newtown Square. Upper Darby. PA.

Project Management Institute, (2004). Book of knowledge, Glossary of terms. PMI.

Ranasinghe, M. (1994). Contingency Allocation and management for building projects. Construction Management and Economics, 12, 233-243.

Rowe, J.F. (2006). A construction cost contingency tracking system (CTS). Cost Engineering, 48(2), 31-37.

Smith, N.J. (1999). Management Risk in Construction Projects. Blackwell Science Ltd, Editorial Offices.

Standards Australia (1999). AS/NZS 4360: Risk management. Homebush, NSW

Thompson, P. A., and Perry, J. G. (1992). Engineering construction risks. London: Thomas Telford.

Touran, A. (2003). Calculation of Contingency in Construction Projects. IEEE Transactions on Engineering Management, 50(2), 135-140.

Wideman, R.M. (1995). Cost control of capital projects and the project cost management system requirements. Richmond, British Columbia: BiTech.

Yeo, K.T. (1990). Risks, classification of estimates, and contingency management. Journal of Management in Engineering, 6(4), 458-470.)

Downloads

Published

2016-03-10

How to Cite

Addo, J. N. (2016). Determination Of Contingency Sum For Building Projects In Ghana. AFRICAN JOURNAL OF APPLIED RESEARCH, 1(1). Retrieved from https://www.ajaronline.com/index.php/AJAR/article/view/152